Eligibility Criteria
Project Categories eligibility criteria, with reference to the National Building Code General criteria:
​
-
Project must be occupied no sooner than January 1st, 2024 and no later than January 31st, 2026 (for all project categories EXCEPT renovation projects).
-
OR Project must be completed no sooner than January 1st, 2024 and no later than January 31st, 2026 (for renovation projects ONLY).
-
-
Project must be occupied by the time of submission
-
Project opaque walls must be comprised of more than 50% EIFS
-
Project site and building must be physically located in Canada
-
Project must not be a previous EIFS Architectural Design Awards Finalist or Winner
​​
Low rise residential:
-
Project must be within the scope of Part 9 of Division B of the NBC and be used or intended to be used residential occupancy
-
Project must be four (4) storeys or under in building height
​​
Mid rise residential:
-
Project must be within the scope of Part 9 of Division B of the NBC and be used or intended to be used residential occupancy
-
Project must be four (4) to six (6) storeys in building height
​​
High rise residential:
-
Project must within the scope of Part 3 of Division B of the NBC and be used or intended to be used residential occupancy
-
Project must be above six (6) storeys, exclusive
​​
Commercial/Retail:
-
Project must be within the scope of Part 9 or Part 3 and be used or intended to be used business and personal services OR mercantile occupancy
​​
Hospitality:
-
Project must be within the scope of Part 9 or Part 3 and be used or intended to be used for short term residential occupancy
-
Project must be a hotel, motel, or lodging house
​​
Recreational/Institutional:
-
Project must be constructed in compliance with the NBC and be used or intended to be used for assembly occupancy
​​
Renovation:
-
Project must be constructed in compliance with the local building code
-
Project must be a recladding of an existing building
-
If an addition was added to an existing building and new floor area was added, the project would not be eligible for the renovation category, but would be eligible for the appropriate category above)
​​
Panelized/prefabricated EIFS Systems:
-
Project must use Panelized/Prefabricated EIFS Systems for at least 80% of its opaque walls
-
Project must be constructed in compliance with either Part 3 or Part 9 of the NBC
Please note: Project categories may be redefined, at the discretion of the judging panel, based on the number of participating projects.